SAILING YACHT – 67 METERS

For the S/Y Vertigo, we carried out work, over a period of three months, at the Navantia shipyard, in Cartagena, Spain.

The work consisted of:

Cleaning the drains (hatches on deck): 

  1. This work consisted of cleaning the drains on the deck and hull, of different diameters. 
  2. An inspection was carried out using special webcams, followed by the corresponding cleaning of the 206 deck drains. 
  3. The drains mentioned were cleaned with a special descaling product and pressurized water.

Hot water circulation system: 

  1. In this work, a new collector was manufactured in 32 mm and 25 mm diameter PPR pipe, and 16 mm multilayer, with the replacement of 2 mixing valves, 10 1'' valves, 2 3/4'' valves, 3 check valves and several links. 
  2. In addition, the necessary adapters with 3 connecting pieces were placed, concluding with the insulation and manufacturing of the pipes.
  3.  In addition, in the three main fresh water pumps, an existing pipe was replaced with a rigid and hard one, with its corresponding pressure gauge, valves and connections.

Finally, the final adjustments and checks of all the work were carried out to ensure its correct operation.